Change orders, lien waivers, pay applications, milestones and retainage for larger projects — and who on your team may work them.
Larger projects come with paperwork that a one-visit job never sees: scope changes mid-build, lien waivers at payment time, billing by pay application or milestone instead of all at once. The construction screens gather those tools in one place under the JOBS tab.
§The four cards
| Card | What it is for |
|---|---|
| CHANGE ORDERS | Changes to scope or price after the original agreement — customer change orders and sub change orders. |
| LIEN WAIVERS | Waivers tied to the payment they cover; signed waivers are locked. |
| PROGRESS BILLING | Pay applications (G702 / G703 format) and milestones, with the contract to date per project. |
| RETAINAGE | What is still held, released, or held more than 90 days, per project. |
§Who may work construction billing
| Role | Access |
|---|---|
| Owner, admin, office, accountant | Every construction screen. |
| Field rep | Only on customers he is assigned to. |
| Door knocker, basic user | None — the screens say it is not part of their role. |
Approving, rejecting or voiding a change order is for owners, admins and the office (the accountant no longer approves).
§Change orders: customer and sub
- ◆A customer change order changes the contract with the homeowner. It moves Draft → Submitted → Approved or Rejected, or Void (a reason is required).
CONVERT TO INVOICEbills it once. - ◆A sub change order changes what you pay the subcontractor. It never bills the customer; once approved it raises the sub's contracted amount on the sub's screens, payouts and the work order.
CREATE CUSTOMER CHANGE ORDERmakes a linked customer draft when the homeowner should pay for it too. - ◆Sub change orders arrive on the
CHANGE ORDERSscreen (filterSUBCONTRACTOR), not in the APPROVALS queue. The sub and the office get a notice on request, approval and rejection. - ◆Only drafts can be deleted. A change order billed through a pay application reads "BILLED (PAY APP No. 2)" and cannot be billed again.
§Pay applications
A project is a customer + job. Applications are numbered 1, 2, 3 … per project, one open at a time, and No. 2 carries No. 1 forward. APPROVE & BILL creates one progress invoice for the payment due; paid, partly paid and void follow that invoice. The PDF footer reads "Pay application (G702 / G703 format) — not an AIA® document". A job is billed either by pay applications or by milestones, never both.
§Retainage
Retainage is set on each pay application or invoice. There is no company-wide retainage default, and releasing retainage does not check for a lien waiver — release only what the screen shows is still held (an over-release is refused).
§The same tools on a customer
The customer's FINANCIALS tab has § LIEN WAIVER, ± CHANGE ORDER and ◆ AIA G702/G703 (it makes a pay application in G702 / G703 format), each opening an in-place modal, and every invoice row carries ± CO.